Business Energy Glossary
What is maximum demand?
Maximum demand is the highest half-hourly electrical load that a business site has drawn over a defined period, measured in kVA (apparent power) or kW (real power). On half-hourly metered electricity supplies, maximum demand drives the sizing of the network connection and is the basis for the Authorised Supply Capacity and the monthly capacity charge. Reviewing maximum demand against the ASC is the standard test for whether the supply is right-sized.
kVA charges on your bill explains the agreed capacity that maximum demand is compared against.
Maximum demand on most UK business sites occurs during a specific operating moment: a hotel during breakfast service, a manufacturing site at the start of a shift, an office on the hottest summer afternoon. Identifying that peak and understanding why it occurs is essential for managing capacity charges and for planning any capacity reductions or upgrades.
On this page
What maximum demand measures
Maximum demand is the highest rate of electricity a site draws in any half-hour, usually measured in kW or kVA. It shows whether your agreed supply capacity is right-sized, and exceeding that capacity can trigger excess capacity charges.
For the full explanation, see What Is Maximum Demand? A Simple Guide for Business Energy.
Maximum demand is the single highest half-hourly average load drawn by the supply over a defined window. The standard measurement period is 30 minutes (matching the half-hourly settlement structure of the UK electricity market).
The figure can be reported as:
- Maximum half-hourly kW (real power) for sites measuring active demand only.
- Maximum half-hourly kVA (apparent power) for sites measuring total demand including reactive component.
For sizing purposes the kVA figure is the one that matters, because the network is sized to carry kVA. Some monitoring systems only record kW; converting requires dividing kW by the power factor at the time of measurement.
Read the full guide, What is maximum demand?, for the detail.
If a figure on your bill doesn’t look right, energy invoice validation checks each charge against your contract and meter data.
maximum demand FAQs
What is maximum demand?
The highest half-hourly electrical load drawn by a business site over a defined period, measured in kVA or kW. It drives the sizing of the network connection and the monthly capacity charge.
How do I find my maximum demand?
Pull half-hourly data from the supplier for the last 12 to 24 months. The supplier or meter operator provides this on request. Maximum demand is the highest single half-hourly figure across the period.
What is the difference between kVA and kW maximum demand?
kW is real power doing useful work. kVA is apparent power including the reactive component used by motors and transformers. The DNO sizes the network on kVA. kVA = kW divided by power factor.
When does maximum demand typically peak?
It depends on the site type. Offices peak mid-morning in summer (cooling + lighting + IT). Restaurants peak during meal services. Manufacturing peaks at shift start. Cold storage peaks on hot summer days.
How can I reduce maximum demand?
Load shifting (move discretionary loads to off-peak), equipment efficiency (LED lighting, modern HVAC, variable speed drives), and on-site generation (solar PV with battery).
What happens if I exceed my ASC?
The DNO charges an excess capacity charge for the excess kVA at typically 2 to 3 times the standard capacity rate. Repeated breaches usually indicate the ASC needs to be increased.